Data Center Description | |
---|---|
Building | Industrial purposed build data center |
Address | Jalan Teknokrat 1/2, Cyber 3, 63000 Cyberjaya, Selangor |
Lift | Passenger lift / Freight lift |
Availability | 99.98% |
Total White Space | Approximately 240,000sqt ft |
Suite Size | Up to 7,000 sqpft |
Floor loading | 15kN/sqm |
Rack Capacity | 220 Racks |
Rack size | 45U |
Data Center Power Supply | |
---|---|
UPS | 2N |
Power connection | Dual Incoming Power Supply (N+1) |
Voltage | 240V/50 Hz, 415V/50 Hz |
Rack Power | 5kW (Upgradeable to 10kW) |
Generator sets | N+1 |
Backup diesel | 48 Hours |
STS & PDU | 32Amp, 24 x 2 PDU (A+B) |
Connectivity | |
---|---|
Network | Carrier Neutrality via MYIX |
Data Cable | Cat 5E, Cat 6 UTP (RJ45 interface), SM/MM (FC/SC/ST/LC) fiber, DS3, E1, Coaxial |
Cooling System | |
---|---|
CRAC | N+1 Water-Cooled Sytem N+2 Computer Room Air Handler |
Temperature | 22°C +/- 3° |
Humidity | 50 RH +/- 10 RH |
Disaster Prevention & Suppression | |
---|---|
Fire suppression | Watermist |
Water leakage | Resistive Leak (Cable) monitoring leakage at any point along the perimeter of the data centre area and surrounding the CRACs |
Security | |
---|---|
Water Leakage Detection | 24/7 On-Site Staffed Monitoring |
Building Security | 24/7 Entrance Security Guards with Multiple-Layered Security Control |
Accreditations | |
---|---|
ISO/IEC 27001 Information Security Management System | |
ISO 9001 Quality Management System | |
ISO/IEC 20000-1 IT Service Management System | |
Payment Card Industry Data Security Standard (PCI DSS) | |
Uptime Institute Tier III Certification of Design Documents | |
Uptime Institute Tier III Certification of Constructed Facility | |
Threat, Vulnerability and Risk Assessment (TVRA) | |
Green Building Index (GBI) |